Clean asset data passes five tests: it's complete, consistent, located, structured and owned. Complete means every asset in scope is in the register and nothing out of scope is. Consistent means the same kind of equipment is named and classified the same way at every site. Located means a tech can walk to it, down to the room. Structured means assets roll up through a hierarchy that matches how the building runs. Owned means a named person keeps the data current after go-live. In my experience, most organizations pass one or two. The CMMS Data Health Scorecard is a quick way to see where you stand.
Yes, and start now, before the first vendor demo. A new CMMS won't clean your data. It will show you, faster and more clearly than the old one did, exactly what you loaded into it. Before go-live, a data problem is a spreadsheet edit. After go-live, it's a change to live records with years of history attached, made by people who are also keeping the buildings running. Directors often ask me whether they should wait for the new system. My answer is always the same: the data work doesn't depend on the software, and the problem usually wasn't the software to begin with.
Track anything that gets scheduled maintenance, that a regulator or accreditor expects to see, whose failure would hurt safety or operations, or whose cost history you'd want for a capital decision. If the answer to all four is no, it probably belongs as a component of a parent asset, or not in the register at all. A small exhaust fan with no PM can live as part of its air handling system. A fire pump never can. Write the answer down as a scope rule before anyone goes into the field, because "we track the important stuff" isn't a rule a field team can apply.
It depends on the size of the portfolio and the state of the starting data, so I don't quote a number before seeing both. What I can tell you is that it takes longer than most project plans allow, and it can't be compressed by adding people in the last month. For a CMMS go-live, I plan the data work to start about six months out: standards first, then a pilot building, then field collection across the portfolio, then cleanup and test loads. The order matters more than the calendar. Standards come before collection, collection before migration, and ownership before go-live.
Your asset register is the evidence a surveyor looks at. CMS expects hospital facility and medical equipment to be listed in an inventory that includes a record of maintenance activities. The Joint Commission expects an inventory with the inspection, testing and maintenance (ITM) activities and frequencies for that equipment, and required activities on high-risk equipment and on high-risk and infection control utility components must be 100 percent complete. If a component isn't in the register, it isn't on an ITM schedule, and you can't show it was maintained. Most of my 25+ years were in hospitals, and missing utility and life safety components are the gap I find most often.
Because a capital request is only as strong as the evidence under it. Install dates, condition and repair history all live on the asset record. When work orders go against the building instead of the asset, or one air handler exists under three names, the history is split and the funding case rests on age instead of performance. I once had to verify a capital request for a 20-year-old generator by calling four or five vendors, because their service reports had never been attached to the asset. Condition assessments need to share asset IDs with the CMMS, too, or the capital plan and the maintenance program run on two different lists.
Agree on the owner's standards before the first piece of equipment is listed, not at turnover. That means the owner's naming convention, location hierarchy, classification and required fields, plus manufacturer, model, serial numbers and warranty start dates. A project management system's equipment list isn't a CMMS, and most turnover lists get rebuilt by hand after occupancy. COBie, maintained by the National Institute of Building Sciences, is a published format for structured handover data, and writing it into contracts costs far less than collecting the data after move-in. For condition assessments, the key is shared asset IDs. I work with primes as a subconsultant on exactly this.
It means my advice doesn't depend on which system you choose. I don't sell or resell CMMS software, so I have no reason to steer you toward one product or talk you into replacing a system that could be fixed. Every system on the market needs the same thing from you: a clean, structured, owned list of what you maintain and where it is. That's where I put my effort. When an owner does need a new system, I help write requirements from the people doing the work, not from a vendor demo, and keep the evaluation objective.
It starts with a conversation about what isn't working: a system nobody trusts, a replacement coming up, a survey on the horizon or a project nearing turnover. From there, the work usually takes one of a few shapes: a health check that tells you whether to fix your current system or replace it, requirements and selection support, owner's-side oversight during implementation, PM and ITM program design, or turnover asset data for construction and assessment projects. I work directly for owners and as a subconsultant to primes. You can call me at (317) 762-5687, email tim@datumassetadvisory.com, or start with the CMMS Data Health Scorecard.
I'm Tim Shirley, a CMMS and asset data specialist based in the Greenwood, Indiana area, and I'm the person you'll work with. I've spent 25+ years in facility management, most of it in hospitals. I started in 1999 as a floor care tech, worked up through maintenance and plant operations, and have served as interim director of plant operations at several hospitals. I was part of a four-person corporate team directing plant operations across 130 hospitals, where we brought sites onto a standard system one at a time. I hold CHFM, CHSP and Lean Six Sigma credentials.